Testing & Commissioning
– Protection and Control Commissioning of Substations
– Objective & Scope: The objective of the commissioning & testing is to verify the correct integration of primary & secondary Protection, Control & Metering Equipment for each Transformer, Motor & Feeder Bay, with the objective of signing each bay off as ready to be energized with primary voltage.
– Testing all Primary Equipment
- Circuit Breakers
- Current Transformers
- Voltage Transformers
- Power Transformers
- NEC/NER/ Auxiliary Transformers
- Surge Arrestors
-Proving Equipment Wiring to Design Drawings
- Circuit Breakers
- Transformer Auxiliary Wiring
- Tap Change Drive
- Control Panel
- Switchgears
– Proving Testing all Secondary Cables
- Continuity
- Insulation resistance
- Core & Cable Numbers
– Apply Relay Settings & Logic
– Perform Secondary injections on Relays & other secondary equipment
– Function test complete scheme